These FAQs explain Primavera P6 software and practical scheduling concepts. For Wiznic World course arrangements and learning options, visit our training FAQs.
Primavera P6 supports project planning and scheduling, including activities, relationships, calendars, resources, costs, baselines and progress updates. The available functions depend on the product, version and configuration. Read our Primavera P6 introduction for an overview.
No. P6 Professional is a desktop scheduling application. P6 EPPM supports enterprise project and portfolio management with web-based capabilities; P6 Professional can also connect to an EPPM database. Oracle Primavera Cloud is a separate cloud application, rather than simply P6 renamed.
A work breakdown structure organises project scope into a hierarchy. Activities represent the scheduled work within that structure. A useful schedule connects the scope with activities, durations, calendars and logical relationships.
A baseline is a retained reference plan used to compare the current schedule with agreed expectations. Baseline selection and change control should follow the project's requirements; replacing a baseline merely to hide variance undermines the comparison.
The data date is the schedule's progress cut-off or status date. Actual progress should be recorded consistently up to that date, with remaining work assessed for the forecast. It is not automatically the same as the date on which you open the software.
Typically, the planner needs actual starts and finishes, remaining durations or work, progress measurements, and information about current constraints and changes. The project should define how progress is collected and checked. Changing percentage-complete values alone is not a complete update process.
The critical path identifies work driving a completion point under the schedule's logic and settings. Float indicates scheduling flexibility calculated against relevant dates. Constraints, calendars and scheduling options can affect the results, so planners should review the logic rather than rely only on a colour or filter.
Yes. Resources and cost inputs can be assigned and analysed when the schedule is appropriately structured and loaded. Useful outputs depend on reliable quantities, rates, productivity assumptions and update rules; the software does not establish those inputs for you.
Requirements vary by release and deployment. Check the documentation for your exact product and version, including supported operating systems, database options and tested configurations. Use Oracle's P6 Professional documentation library rather than assuming a universal RAM, processor or database specification.
Compare the specific editions and your project's requirements: schedule complexity, shared data, reporting, integration, available skills and client submission standards. Avoid choosing solely on project size or assuming that one application is always better.
No. Effective scheduling also requires scope interpretation, execution logic, resource assumptions, progress measurement and forecast explanation. Wiznic World connects software practice with project planning and controls, guided by Madan Maharana, with 27+ years of industry experience and Primavera teaching since 2007.
Explore Primavera P6 training, the LBMF training program and our exam and certification guide. A provider's course-completion certificate is different from an Oracle certification; verify current external exam requirements with Oracle.